Old Newton School

Background & Brief

Old Newton Primary School is situated 3 miles North of Stowmarket in a rural setting close to St Mary’s Parish Church, in the village of Old Newton, Suffolk. Originally built in 1859, the school was extended in 1999 and 2008 and comprises a collection of buildings with capacity for 105 pupils.​

In 2023 the school secured funding to create a new self-contained classroom and library in an underused area overlooking the playground. A prefabricated volumetric solution was initially considered, but rejected on the grounds of limited design options, questions of longevity and potential air quality issues arising from mostly petrochemical derived internal finish materials. In 2024 the school governors approached IF_DO Architects and Natural Building Systems to propose an off-site manufactured solution using regenerative, natural materials. ​

Central to the school’s ambition was the need for a flexible teaching space with a seating area overlooking the playground, and excellent indoor air quality, free from VOC’s and other contaminants. Moreover, the new classroom would need to be delivered and built rapidly, with disruptive operations occurring only during school holidays.​

Design Development & Delivery

IF_DO developed a concept design with support from Natural Building Systems using mostly standard ADEPT® components. Following early consideration of a suspended deck, a conventional ground bearing slab was specified to address ground conditions. The project was tendered and let in January 2024 under a Design and Build contract to local builders, Mixbrow Construction, with NBS nominated to design and supply the superstructure elements (including SE design).​

Following an award of funding from the Digital Innovation Fund NBS engaged Circuland to provide Digital Material Passports and LCA support.​

Ground works commenced in September 2024 with the NBS components delivered in October. Mixbrow completed the project in December 2024​

A detailed LCA is currently pending.​

Key information

Location: Old Newton, Suffolk

Architects: IF_DO Architects

Structural Engineer:

Contractor: Mixbrow Construction

Project type: New-build 

Sector: Educational

Size: 71 m2  

Project stage: full completion

Old Newton, Suffolk

February 2025

Classroom